Prepare your audit schedule. Normally internal audits every 3 months |
|
|
Review the contract scope and prepare your questions in accordance with ISO system elements. |
|
|
Complete correspondence to all parties concerned notifying them of audit. This is normally completed two weeks prior to the audit. |
|
|
|
Conduct audit open meeting with all parties concerned. Explain the system elements that are going to be audited. Introduce other members of the audit team. |
|
|
Make sure departmental engineers have not left the office for site.
Record your answers and be polite. |
|
|
Audit reports are completed within three working days
and the initial findings are discussed in the Audit close out meeting. Internal Audits are normally completed every three months. |
|
|
| Resolution of non
conformance reports and corrective actions |
|
Make every effort to identify possible nonconformances. Try and make clear the audit is a business tool that benefits every one. |
|
|
Lead audit completes audit close out meeting and highlight the scope and results on the audit. |
| AUDIT REPORT DISTRIBUTION
|
|
| Distribution of
Audit Report |
|
Distribute your audit report to all the members of the audit opening meeing. Discuss with management ways and means to improve performance. |