| 1. Material Evaluation and Approvals |
 |
- Supplier
- Mix designs & Trail Mixes
- Rebars & accessories
- Embedments
|
|
 |
| 2. Inspection |
 |
- Survey & verification
- Compaction testing (foundations)
|
|
 |
| 3. Erection |
 |
- Forms
- Rebars
- Embedments
- Accessories
|
|
 |
| 4. Inspection |
 |
- Pre- Concrete inspection
- Survey report
- Compaction test report
- Complete inspection check list
|
|
 |
| 5. Concrete Pour Inspection |
 |
- Trip ticket verification
- Slump Test
- Temperature check
- Cylinder sampling & casting
|
|
 |
| 6. Concrete Curing |
 |
|
|
 |
| 7. Compressive Testing |
 |
- Three,seven and 28 days
4.000 psi min on 28 days
|
|
 |
| 8. Completion of
The Work |
|